The Federal Energy Regulatory Commission (FERC) voted Feb. 15 to extend the completion deadline of Tellurian’s Driftwood project to April 2029.
Near Lake Charles, Louisiana, the Driftwood project has already received permitting permission from the U.S. Department of Energy, meaning the facility is not subject to the pause the Biden administration placed on new LNG projects in January. The project includes a pipeline and an LNG export terminal that will have a capacity of about 27.6 MMmt/year when completed.
According to the FERC, Tellurian applied for the extension in October 2023. In the extension application, the company stated it had worked diligently toward project completion but had been delayed by COVID-19’s effect on the supply chain. The company also said it needs time to secure customers and financing.
Tellurian now says the earliest phase 1 of the project could be completed is in late 2027.
Environmental group Sierra Club argued against the extension request, saying that Tellurian has mismanaged the project and that decision requires additional study to assess the environmental impact of the project. The FERC rejected the Sierra Club’s arguments in its decision.
Earlier in February, Houston-based Tellurian announced plans to sell its natural gas assets in the Haynesville Shale, using part of the proceeds to focus on development of the Driftwood project.
“Tellurian thanks FERC for working with our team to ensure the safe construction of Driftwood LNG. FERC has been diligent in its oversight, having visited the site 19 times already, and provided careful examination of this extension request,” said Tellurian CEO Octávio Simões. “We have invested over a billion dollars into Driftwood LNG’s development, we have our approval to export and all applicable construction permits, and we are eager to provide the world with liquefied natural gas exports.”
Recommended Reading
Ithaca Energy to Buy Eni's UK Assets in $938MM North Sea Deal
2024-04-23 - Eni, one of Italy's biggest energy companies, will transfer its U.K. business in exchange for 38.5% of Ithaca's share capital, while the existing Ithaca Energy shareholders will own the remaining 61.5% of the combined group.
Triangle Energy, JV Set to Drill in North Perth Basin
2024-04-18 - The Booth-1 prospect is planned to be the first well in the joint venture’s —Triangle Energy, Strike Energy and New Zealand Oil and Gas — upcoming drilling campaign.
EIG’s MidOcean Closes Purchase of 20% Stake in Peru LNG
2024-04-23 - MidOcean Energy’s deal for SK Earthon’s Peru LNG follows a March deal to purchase Tokyo Gas’ LNG interests in Australia.
Equinor Acquires Stake in Standard Lithium Smackover Projects
2024-05-08 - Equinor’s transaction, completed effective May 7, includes interests in Standard Lithium’s flagship South West Arkansas Project and East Texas properties.
Crescent Point Divests Non-core Saskatchewan Assets to Saturn Oil & Gas
2024-05-07 - Crescent Point Energy is divesting non-core assets to boost its portfolio for long-term sustainability and repay debt.